Ragmet Engineers undertake Heat Maintenance Jobs. Our dedicated team of experts is committed to ensuring the seamless operation and longevity of your heating systems. With meticulous attention to detail and cutting-edge techniques, we offer comprehensive maintenance solutions tailored to your unique requirements. From routine inspections to proactive repairs, trust Ragmet Engineers to keep your heat systems running smoothly and efficiently.
| Sr. No. | Client | Nature of Jobs |
|---|---|---|
| 1 | HPCL | Provision of sliding blinding for positive isolation of APH of FRE APS Furnace 31F1 |
| 2 | BPCL | Job on CMU heater F01 & FPU B1 Heater |
| 3 | HPCL | Miscellaneous Tube Replacement Job in Furnace F 601 |
| 4 | BPCL | Work on HCP Heater (H-801) during HCPU S/D in Sept/Oct 99 |
| 5 | BPCL | To carry out replacement of HVU Heater Roof ARCH plate during FCCU complex S/D in Sept.Oct'99 |
| 6 | BPCL | Jobs on FCCU charge heater 20F01 & high vacuum unit |
| 7 | BPCL | Work on HCP heater (H801) during HCPU Shutdown |
| 8 | BPCL | Replacement of HVU Heater Roof Arch plate during FCCU |
| 9 | BPCL | Replacement of Additional tubes in 12 F01 heater during ongoing FCCU Complex shutdown |
| 10 | BPCL | Work on heaters F101/F102 F320 in ARU/RFU S/D. |
| 11 | BPCL | work on heaters F101 / F102 F320 in ARU / RFU Shutdown |
| 12 | HPCL | Cleaning scaffolding tube replacement & miscellaneous jobs in F-101-LR-VPS Furnace |
| 13 | HPCL | BC-F-1001(32-F-1) & BC-F-1101 (32-F-1) Furnace, Air-Preheaters & Ducts Jobs (TA/98) |
| 14 | HPCL | VP-F-1801 (12-F-1)&14-F-1 Furnaces Air-Preheaters & Ducts Jobs.(TA/98-99) |
| 15 | HPCL | PF-F-3&4 Furnaces Air Pre-heater& Ducts job(TA / 98 - 99) |
| 16 | HPCL | cleaning scaffolding decoking tube replacement & miscellaneous jobs in F-101-LR Furnace Nov/Dec-96 S/D. |
| 17 | HPCL | Repair / Replacement jobs in BC -F-1101 Fuels refinery Sep.1996 shutdown |
| 18 | HPCL | casing replacement & other Misc.Mech.jobs in BC-F-1001 Sept - 96 shutdown |
| 19 | HPCL | casing replacement & other Misc.Mech.jobs in BC-F-1001 Sept - 96 shutdown |
| 20 | HPCL | Burner housing repair of PF F3/F4 FR |
| 21 | ONGC | Mechanical Cleaning of crude oil exchange at yard in ONGC urban and replacement of defective tube and re-installation of exchanger at Offshore. |
| 22 | BPCL | To Repair HRSG / HEB ECO Coil at CPP. B/H |
| 23 | HPCL | Provisions of TST Points, Decoking and other Jobs in FuranceF-40L in SEU-1, LR |
| 24 | BPCL | Jobs on Column/Heaters in HCPU shutdown. |
| 25 | BPCL | Jobs on Vessels - Columns - Relief Valves in FCCU Shutdown Jobs. |
| 26 | BPCL | Jobs on Vessels - Columns - Relief Valves in HCPU Shutdown Jobs . |
| 27 | RCF/UB | Replacement of Heater Tubes |
| 28 | BPCL | 001B2 Heater APH module replacement |
| 29 | RCF/UB | Replacement of Reformer Tubes in methanol plant |
| 30 | RIL | Crude Heaters Cold Beam Jobs |
| 31 | TATA | Jobs on Diverter Damper & Condensate external pre heater |
| 32 | TATA | Replacement of small sized HP valves and steam nuts of isolating valves of HP FW heaters |
| 33 | BPCL | Tube Bending job of DHDS Reformer Heater hair Pin Tubes |
| 34 | HPCL | GFEC S/D: Jobs in Furnace 11F1 & 11F2 at APS FR |
| 35 | HPCL | GFEC S/D: Opening & other mech. In SEU III unit |
| 36 | HPCL | GFEC S/D: Opening & other mech. In SEU I & II unit |
| 37 | HPCL | Repair jobs of 11APH1 |
| 38 | HPCL | GFEC S/D: Opening & other mech. Jobs |
| 39 | BPCL | FO2 Tube Sheet Replacement in CDU S/D |
| 40 | HPCL | TA 2005: Misc. mech. Repair jobs in Furnace 12F1 at VPS FR |
| 41 | HPCL | Misc. mech. Repair jobs in Furnace |
| 42 | HPCL | Mechanical repair job in SEU2 S/d |
| 43 | HPCL | S/D job in FRE VPS Furnace |
| 44 | BPCL | Water washing of HVU Heater 12F01 during S/d |
| 45 | HPCL | F-601 Repair Job |
| 46 | HPCL | Tube replacement 7 Miscellaneous repairs in VPS |